MEETING DATE: 4/17/2018

AGENDA ITEM: *6F. Contract to Remove and Replace 2 Welded Steel Vessels

DATE PREPARED: 3/19/2018

DISTRICT NO.:3 & 5

STAFF LIAISON: Chris Williams, Construction/Procurement, (623) 349-6225, cwilliams@buckeyeaz.gov

 

DEPARTMENT: Construction and Contracting

AGENDA ITEM TYPE:Consent Item

ACTION / MOTION: (This language identifies the formal motion to be made by the Council)

Council to take action on the Construction Contract (No. 31800038) between the City of Buckeye and MMI Tank & Industrial Services, Inc. for the removal and replacement of two steel water vessels at the Sundance Booster Station.


RELEVANT GOALS:
GOAL 4: Adequate, Well-Maintained and Well-Planned Public Infrastructure

SUMMARY

PROJECT DESCRIPTION: 

The Water Resources Department requires the removal and replacement of two (2) existing welded steel vessels used for water treatment. The condition of the steel vessels are failing due to coating issues, cathodic protection issues or small leaks. The contract shall include all material, surface preparation, material application, inspection and testing, and handling and disposal of all debris. The two welded steel tanks are located at the Sundance Booster Station, 22900 W. Yuma Road, Buckeye, Arizona 85326.

 

The Construction and Contracting Division issued a Request for Proposals on February 8, 2018, followed by a pre-proposal meeting and site visit on February 21, 2018. Proposals were due on March 1, 2019, with two contractors submitting proposals as follows:

 

MMI Tank & Industrial Service, Inc.

Revaluation Industrial, LLC.

 

After review of the submittals by a three members evaluation committee, it was determined that MMI Tank & Industrial Services, Inc. was the responsive and responsible bidder and best suited for this project.


BENEFITS:

Fully functioning welded steel vessels.


FUTURE ACTION: Council and staff; does this need to be communicated internally/externally?
None


FINANCIAL IMPACT STATEMENT: Must be completed before submission

Contract in the amount of $330,577.00



CURRENT FISCAL YEAR TOTAL COST:
BUDGETED


FISCAL YEAR:
2017/2018


FUND/DEPARTMENT:
40003213-520582


ATTACHMENTS:
Description
Contract
Vicinity Map